Practical guidance on federal acquisition policy, PPBE, audit remediation, and program management from the team supporting TSA and DHS components.
GAO (Nov 18): none of 21 agencies fully met all five OMB data center acquisition and operating requirements before they expired Sept 30.
GAO (Nov 16): clean opinions on SEC and Investor Protection Fund statements, effective internal control, and no reportable noncompliance.
GAO (Nov 18): CMS’s vulnerability process misses fraud risks and does not assess likelihood, impact, or control suitability; four recommendations.
On November 18, 2026, the Government Accountability Office released Federal Data Centers: Congress Has an Opportunity to Improve Agencies’ Acquisition and Operations (GAO-27-108971). It is GAO’s third and final annual review under the Federal Data Center Enhancement Act of 2023 (FDCEA). In response to that law, the Office of Management and Budget (OMB) established five minimum requirements in January 2025 for acquiring and operating federal data centers, and agencies were to satisfy them by January 14, 2026 for agency-operated data centers, with potentially later dates for contractor-operated ones. Of the 24 Chief Financial Officers Act agencies, 21 reported having data centers. As of August 2026, none had fully addressed all five requirements.
The scorecard is uneven. Ten agencies fully addressed making key data center decisions at the agency level, and ten fully addressed monitoring operations with automated tools—although GAO noted that for nine agencies that reported using such tools, the documentation provided did not always reflect it. Only two agencies fully met mission availability requirements and four fully met information and physical security requirements; the rest were partial. Many agencies said they met availability requirements but could not show a process for managing risks to determine the maximum tolerable duration and frequency of downtime. All five agencies with new data centers only partially incorporated energy and water usage into decision-making. Because the OMB requirements expired on September 30, 2026 under the act, GAO made no recommendations to agencies; instead it suggested that Congress consider reauthorizing the FDCEA or replacing it with a new law, noting that growing agency use of artificial intelligence has increased demand for high-performance computing.
What it means for acquisition teams: a mandate lapsing does not make the underlying requirements less sensible. Decision authority at the agency level, automated monitoring, defined availability, security, and resource-use considerations are simply good acquisition practice for any hosting, colocation, or data center service. The most common gap GAO found was not a missing capability but missing evidence—claims of monitoring or availability that the documentation did not support. That is a contract-administration and records problem that acquisition offices can fix now, especially for contractor-operated facilities where requirements live in the contract or nowhere.
Practical steps: keep the five requirements in acquisition strategies and statements of work for data center and hosting services; require availability targets that state the maximum tolerable downtime and tie them to a documented risk analysis; make automated monitoring data a contract deliverable rather than a verbal assurance; include energy and water usage in the evaluation of new capacity; and retain the evidence in the contract file so compliance can be demonstrated when Congress or an auditor asks. Watch for legislative action that could reinstate or update the requirements.
Source: U.S. Government Accountability Office, “Federal Data Centers: Congress Has an Opportunity to Improve Agencies’ Acquisition and Operations,” GAO-27-108971, November 18, 2026.
On November 16, 2026, the Government Accountability Office released Financial Audit: Securities and Exchange Commission’s FY 2026 and FY 2025 Financial Statements (GAO-27-108840). GAO found that the financial statements of the Securities and Exchange Commission (SEC) and its Investor Protection Fund (IPF), as of and for the fiscal years ended September 30, 2026 and 2025, are presented fairly in all material respects in accordance with U.S. generally accepted accounting principles; that the SEC maintained, in all material respects, effective internal control over financial reporting for both the SEC and the IPF as of September 30, 2026; and that there was no reportable noncompliance for fiscal year 2026 with the provisions of laws, regulations, contracts, and grant agreements GAO tested. GAO also reported that the SEC collected $4.42 billion in penalties for securities law violations in FY 2026, some of which goes to the IPF to pay whistleblower awards and support investor education.
The structure behind the opinion is worth noting. The SEC is required by law to prepare and submit audited financial statements each year, and the Securities Exchange Act, as amended by the Dodd-Frank Act, requires a separate, complete set of audited statements for the IPF. Section 963 of Dodd-Frank also requires the SEC to report annually on management’s responsibility for internal control over financial reporting and its assessment of that control’s effectiveness, with the Chair and Chief Financial Officer attesting to the report—and requires GAO to evaluate and report on that assessment. In other words, management makes and signs its own assessment first, and the auditor tests it.
What it means for audit remediation teams: a clean opinion is an outcome, not a project. It reflects a management assessment that can stand on its own evidence, a separate readiness effort for every fund or component with its own reporting requirement, and compliance testing that turns up nothing reportable. For agencies still working down material weaknesses or significant deficiencies, this is a useful picture of the end state—and a reminder that the audit cycle is tight, with this report issued about seven weeks after fiscal year-end.
Practical steps: inventory every statutory reporting requirement, including fund-level or component statements, and assign an owner and readiness plan to each; run management’s internal control assessment on documented, testable controls so leadership can attest with confidence; build the provided-by-client calendar backward from a mid-November issuance date; track compliance with the laws and agreements your auditor will test; and treat each year’s clean result as something to re-earn by keeping control documentation and walkthroughs current as systems and staff change.
Source: U.S. Government Accountability Office, “Financial Audit: Securities and Exchange Commission’s FY 2026 and FY 2025 Financial Statements,” GAO-27-108840, November 16, 2026.
On November 18, 2026, the Government Accountability Office released Medicare: HHS and CMS Should Better Manage Fraud Risks (GAO-27-109072). The Centers for Medicare & Medicaid Services (CMS) reported spending nearly $481 billion on benefits for about 34 million beneficiaries in the traditional Medicare Fee-for-Service program in 2025, and Medicare has been on GAO’s High Risk List since 1990. CMS’s Center for Program Integrity (CPI) manages fraud risks through its Vulnerability Management (VM) Process. GAO found that process is broader in scope and does not fully reflect the range of fraud risks facing Medicare; drawing on Inspector General reports, GAO identified fraud risks that CPI had not identified or assessed.
The gaps are in the core mechanics of risk assessment. According to GAO, the VM Process does not assess the likelihood and impact of fraud risks or examine whether existing mitigating controls are suitable. For example, CPI identified a vulnerability in the supplier enrollment screening process—which GAO considers a significant fraud risk because of its association with cases of alleged Medicare fraud, noting that medical equipment suppliers could potentially circumvent screening—but did not assess its likelihood and impact as a fraud risk. GAO made four recommendations: establish a mechanism for CPI to regularly report identified fraud risks and antifraud efforts to HHS’s Assistant Secretary for Financial Resources; finalize CPI’s draft Medicare Fee-for-Service Risk Management Framework guidance; update and finalize draft risk assessments and vulnerability summaries; and update the VM Process to include regular, comprehensive fraud risk assessments consistent with leading practices and internal control requirements. HHS agreed with three and disagreed with one; GAO maintains all four remain valid.
What it means for enterprise risk managers: a list of vulnerabilities is a starting point, not an assessment. Without likelihood and impact, leaders cannot rank risks or decide where to spend scarce program integrity resources, and without evaluating whether controls actually fit each risk, there is no basis for stating residual risk. Draft guidance and draft assessments carry little weight until they are finalized and used. And program-level risk work only informs enterprise decisions if there is a defined channel to report it upward.
Practical steps: compare your risk register against external evidence—Inspector General reports, audit findings, and enforcement cases—to find schemes you have not captured; score each fraud risk for likelihood and impact against a documented risk tolerance; test whether existing controls are designed to address each specific risk; set deadlines to finalize draft frameworks and assessments; and establish a recurring report from program integrity staff to the enterprise risk or financial management function so fraud risk is visible where resources are allocated.
Source: U.S. Government Accountability Office, “Medicare: HHS and CMS Should Better Manage Fraud Risks,” GAO-27-109072, November 18, 2026.
On November 5, 2026, the Legal Services Corporation (LSC) published a final rule in the Federal Register, Cost Standards and Procedures; Purchasing and Property Management (45 CFR Parts 1630 and 1631), effective June 1, 2027. The rule revises the cost allowability, prior approval, and property and procurement standards that apply to LSC grant recipients. Its headline change raises the prior approval threshold from $25,000, where it has sat since 2017, to $50,000. For costs shared between LSC funds and other funding sources, prior approval is required when the portion allocable to LSC funds exceeds $50,000.
The rule also fixes a drafting inconsistency that had caused uneven application: one section said “$25,000 or more,” another said “more than $25,000.” Just as important, LSC clarified that recipients must obtain prior approval before incurring a legal obligation to spend LSC funds above the threshold—giving procurement staff a clear trigger point for planning. The rule keeps LSC’s 30-day decision window for personal property, service contracts, and capital improvements (60 days for real estate), with a 20-day notice if more information is needed, while giving LSC more flexibility on complex requests and clarifying documentation expectations. LSC says the changes grew out of a 2022 retrospective review and discussions with its compliance office and Office of Inspector General. In a companion notice of proposed rulemaking published the same day, LSC proposes removing the dollar threshold from the definition of “capital improvement” so that improvements are tracked consistently regardless of size; comments are due December 21, 2026.
What it means for acquisition and grants teams: a higher threshold is not a lower standard. Recipients of any federal award should treat a threshold change as a prompt to revisit their procurement procedures—confirm the trigger is tied to the date of obligation, not the invoice; check how shared-cost allocations are calculated before deciding whether approval applies; and make sure the documentation package is complete before the clock starts. Fewer transactions needing approval means the ones that remain will draw closer review.
Practical steps: update written procurement policies and contract-approval checklists before the June 2027 effective date, train program and finance staff on the “legal obligation” trigger, and log every near-threshold purchase so auditors can see why approval was or was not sought. Organizations with real property should read the capital improvement proposal and consider commenting by December 21.
Sources: Legal Services Corporation, final rule, “Cost Standards and Procedures; Purchasing and Property Management,” Federal Register Doc. 2026-22649, November 5, 2026; Legal Services Corporation, proposed rule, “Purchasing and Property Management,” Federal Register Doc. 2026-22650, November 5, 2026.
On November 5, 2026, the Government Accountability Office released Superfund: EPA Should Collect and Use Information on the Effectiveness of Its Recovery of Cleanup Costs (GAO-27-107925). The Environmental Protection Agency (EPA) uses the Hazardous Substance Superfund Trust Fund to pay for cleanups when responsible parties cannot be found or cannot pay, and then seeks to recover those costs. GAO found that from fiscal years 2006 through 2024 the Trust Fund received about $34 billion (constant 2024 dollars), mostly from General Fund transfers, and that EPA spent about $25.8 billion at nonfederal National Priorities List sites from FY 1996 through 2024. GAO estimates EPA recovered less than half of that amount.
EPA has identified at least one potentially responsible party for most of these sites, but GAO points to fewer experienced search staff over the last 10 to 15 years and limited ability to hold parties liable. The core finding is a measurement gap: EPA has performance goals and measures to make sure cost recovery steps happen on time, but nothing that assesses how effective recovery is across sites. EPA officials said recovery is a continuous, multi-year process. GAO responded that measuring effectiveness—for example, by region—would show how much of the billions spent is coming back and which efforts work best. GAO made three recommendations: set goals for cost recovery effectiveness, routinely collect performance information on it, and use that information to assess progress and inform decisions. EPA agreed.
What it means for financial management teams: any program that spends first and recovers later—overpayments, reimbursable agreements, debts referred for collection, or cost-share billings—carries the same risk. Process metrics (“was the demand letter sent on time?”) are useful, but they don’t tell leadership whether money is actually coming back. Without an outcome measure, it is hard to justify staffing, target enforcement, or estimate collectible receivables with confidence.
Practical steps: pair each timeliness measure with an outcome measure such as dollars recovered as a share of dollars eligible for recovery; track results by region or office so differences become visible; age outstanding amounts so allowance estimates rest on actual collection history; and report these figures regularly to the people who decide resourcing. A recovery program that is measured only on speed can look healthy while most of the money stays unrecovered.
Source: U.S. Government Accountability Office, “Superfund: EPA Should Collect and Use Information on the Effectiveness of Its Recovery of Cleanup Costs,” GAO-27-107925, November 5, 2026.
On November 5, 2026, the Government Accountability Office released U.S. Patent and Trademark Office: Patent Backlog Reduction Efforts Pose Risks to Examiner Retention and Examination Quality (GAO-27-108491). The backlog of unexamined patent applications reached about 838,000 in January 2025, and in September 2025 the USPTO set a goal of getting it under 599,000—without a time frame. To get there, the agency required examiners to review more applications, decreased examiner training, and expanded AI patent search tools. By August 2026 the backlog was down to about 756,000, but average applicant wait time for a final patentability decision had risen 11 percent since January 2025.
GAO’s modeling shows the workforce is the binding constraint. Examiner attrition climbed from 2.9 percent in FY 2020 to 7.6 percent in FY 2025, and the 12-month rate was still 7.6 percent as of August 2026. Even with examiners doing more work, GAO concluded the USPTO is unlikely to reach its goal before 2031 unless attrition falls. Stakeholders told GAO that higher quotas and eliminating subject-matter training time could keep attrition high and reduce examination quality, that the AI search tools do not yet reliably return useful results, and that the agency paused a survey that had captured stakeholder views on quality. GAO recommended that the USPTO assess and address the risks its backlog reduction efforts pose to retention and quality; the agency did not provide comments.
What it means for program managers: a production target set without a workforce model is a guess. Pushing more throughput per person and cutting training can show early progress while quietly eroding the capacity needed to finish. When a new tool is part of the plan, its benefits should be validated before staffing assumptions depend on it.
Practical steps: build the backlog or workload target on a staffing model that includes realistic attrition and hiring lag; set a deadline so progress can be judged; keep at least one quality measure and one workforce health measure alongside throughput; protect core training time or document the risk of cutting it; and keep feedback channels such as customer and staff surveys running while major changes are under way.
Source: U.S. Government Accountability Office, “U.S. Patent and Trademark Office: Patent Backlog Reduction Efforts Pose Risks to Examiner Retention and Examination Quality,” GAO-27-108491, November 5, 2026.
On October 21, 2026, the U.S. Consumer Product Safety Commission (CPSC) Office of Inspector General issued Management and Performance Challenges for Fiscal Year 2027 (Report 27-O-01). For the second year, the Inspector General ranked Enterprise Risk Management first, ahead of Resource Management and Information Technology Security. The memo explains why: under traditional silo risk management, each leader manages risk in their own area, and some risks “fall between the silos”—for example, a facilities lease change that carries financial reporting consequences the chief financial officer never hears about.
The report credits real progress. The agency reports that every assessable unit completed a risk assessment for the first time by the end of FY 2024; in FY 2025 it updated its risk management guidance to align with FMFIA, OMB Circular A-123, and the DATA Act; and in FY 2026 it revised its Risk Management Council charter, issued a directive requiring offices to document their programs against mission-aligned criteria, and now reports a risk register reviewed weekly by senior leaders. The constraint is capacity: the agency has been without an internal controls auditor for more than two years and could not contract for A-123 support for part of FY 2026. On October 23, the OIG’s FY 2026 FISMA audit (Report 27-A-01) showed the same pattern in cybersecurity—ten prior recommendations closed, but an overall maturity of Level 3 (Consistently Implemented), short of the Level 4 considered effective, with five of eight recommendations tied to prior-year deficiencies.
What it means for ERM teams: a risk register and a council are necessary but not sufficient. Map each top risk to the specific internal controls that address it and to a named owner who can test those controls, so that the ERM profile and the A-123 assurance work reinforce each other instead of running as separate exercises. Build cross-functional review into the register—facilities, IT, human capital, and finance should see each other’s risks—and treat repeat audit findings as a risk signal in their own right. Finally, plan for the control-testing capacity your ERM program depends on, whether staff or contract support, so a staffing gap does not quietly stall assurance.
Sources: U.S. Consumer Product Safety Commission Office of Inspector General, “Management and Performance Challenges for Fiscal Year 2027,” Report 27-O-01, October 21, 2026, oversight.gov; and “Audit of the CPSC’s FISMA Implementation for FY 2026,” Report 27-A-01, October 23, 2026, oversight.gov.
On October 21, 2026, the Department of Energy Office of Inspector General posted audit report DOE-OIG-27-03, covering costs incurred and claimed for fiscal years 2022 and 2023 under the management and operating contract for Idaho National Laboratory (Contract No. DE-AC07-05ID14517). The audit, dated October 14 and performed for the OIG by the Department of the Interior’s Interior Business Center under generally accepted government auditing standards, examined roughly $1.63 billion in FY 2022 and $1.82 billion in FY 2023 costs to determine whether they were allowable, allocable, and reasonable. Because the full report contains controlled unclassified information, the OIG released a public highlights document.
The auditors questioned almost $5 million of education costs within the fringe pool and a net of approximately $700,000 in safeguards and security pool costs. The largest item was more than $30.5 million in proposed award fee amounts in the general and administrative (G&A) pool: award fee is a contractual incentive paid by the Department, and it was questioned because it had been included as a cost in the G&A pool. The auditors reconciled the proposed fee to the general ledger and to the fee the Department determined was earned. The contractor nonconcurred; the auditors maintained their position, and the OIG recommended that the contractor work with the contracting officer to resolve the questioned costs.
What it means for financial management and accounting teams: indirect cost pools are only as clean as what flows into them. Maintain a documented map of which general ledger accounts feed each pool, and test it each year against the contract’s cost principles and any advance agreements—especially for fringe-type benefits, security, and anything that represents profit or fee rather than cost. Reconcile fee earned, fee billed, and fee recorded so that fee never travels through an expense pool. When an incurred-cost submission is challenged, a clear trail from ledger to pool to claimed amount shortens resolution with the contracting officer.
Source: U.S. Department of Energy Office of Inspector General, DOE-OIG-27-03, “Battelle Energy Alliance, LLC’s Costs Incurred and Claimed for Fiscal Years 2022 and 2023 Under Contract No. DE-AC07-05ID14517,” report dated October 14, 2026, posted October 21, 2026, energy.gov/ig.
On October 21, 2026, the Treasury Inspector General for Tax Administration (TIGTA) issued The IRS Must Do More to Address Noncompliance and Potential Misconduct With Return Preparers (Report 2027-IE-R001). Anyone who prepares federal tax returns for compensation must hold a valid, active Preparer Tax Identification Number (PTIN), renewed annually, and the IRS uses PTINs to track preparer behavior such as filing methods, return volumes, and refunds claimed.
TIGTA found that in Processing Year 2025, more than 38,000 preparers with a noncompliant PTIN status—for example, expired—prepared over 2 million returns; nearly 12,000 of them filed only refund returns, about 95,000 Form 1040s claiming nearly $600 million. Between 2010 and 2025, 73 PTINs were issued or renewed for deceased individuals and prisoners, and with no process to prevent it, 691 current IRS employees held active PTINs, more than 90 of whom potentially prepared returns for compensation. Preparers whose returns showed characteristics of an overstated-withholding scheme requested about $740 million in refunds for Tax Years 2023 and 2024. TIGTA made one recommendation—finalize and implement a data-driven return preparer strategy covering outreach, penalties, employee PTIN policies, scheme promoters, and ghost preparers—and the IRS agreed.
What it means for data and analytics teams: any program that issues credentials, registrations, or vendor IDs is running an identity data system, and its controls are only as good as its matches against authoritative sources. Build routine checks against death records, incarceration data, and internal employee rosters at issuance and every renewal, not just at enrollment. Make status a live data element: flag transactions submitted under expired or inactive identifiers, and profile the patterns—such as refund-only activity—that separate routine lapses from higher-risk behavior. Finally, give the strategy measurable outcomes so analytics drives enforcement and outreach instead of sitting in a report.
Source: Treasury Inspector General for Tax Administration, Report 2027-IE-R001, “The IRS Must Do More to Address Noncompliance and Potential Misconduct With Return Preparers,” October 21, 2026, oversight.gov.
On October 5, 2026, the General Services Administration published a proposed rule in the Federal Register (91 FR 63243; GSAR Case 2026-G502) to amend GSAR part 541, Acquisition of Utility Services. It pairs with the FAR Council’s Revolutionary FAR Overhaul rule for FAR part 41 (FAR Case 2026-002), which would keep in the FAR only the utility rules that apply when the Department of Defense and Department of Energy use their special statutory authorities, and would direct all other buys to follow procedures and guidance established by GSA. Comments are due November 4, 2026.
Under proposed GSAR 541.501, agencies must follow GSA’s utility procedures and guidance posted at gsa.gov/utilities, and the rule directs agencies to contact GSA before making a utility-related acquisition so GSA can recommend the most efficient vehicle—typically a GSA areawide contract. Proposed GSAR 541.502 sets up an email-based path for requesting GSA contracting assistance or a delegation of contracting authority. The familiar FAR part 41 provisions and clauses would move into the GSAR as 552.241-1 through 552.241-15, still prescribed on a “substantially the same as” basis, covering items such as electric service territory compliance, connection charges, termination liability, cooperative membership, and economic price adjustment for deregulated electric supply. GSA estimates only minimal familiarization costs.
What it means for acquisition and facilities teams: treat this as a relocation plus a new front door, not a new policy regime. Inventory your current utility contracts and areawide authorizations, then map every FAR 52.241 clause in your templates and contract-writing system to its proposed GSAR 552.241 counterpart so the changeover does not leave clause gaps at the next modification or renewal. Build the “contact GSA first” step into your acquisition planning timeline and document it in the file, and if your component relies on its own utility-contracting authority, confirm now whether that authority is one of the FAR 41.103 special authorities or whether you will need to request a GSA delegation.
Source: General Services Administration, “General Services Administration Acquisition Regulation; GSAR Implementation of Executive Order 14275, Acquisition of Utility Services,” proposed rule, Federal Register, October 5, 2026 (91 FR 63243; GSAR Case 2026-G502), federalregister.gov.
On October 7, 2026, the Government Accountability Office issued GAO-27-108416, IT Dashboard: Selected Agencies’ Investment Ratings Fail to Fully Consider Risks. The Federal IT Dashboard is meant to show how likely each major IT investment is to accomplish its goals, using Chief Information Officer (CIO) risk ratings. GAO selected 53 major investments with at least $35 million in development activity across 12 agencies, built its own risk assessments from investment documentation, and compared them with the published CIO ratings.
GAO’s assessments matched the CIO rating 27 times, showed more risk 24 times, and showed less risk only twice. Two causes drove the gaps: 21 of the 53 ratings were not updated on time under the agencies’ own processes, and two agencies ran rating cycles longer than the quarterly cadence OMB guidance calls for. GAO also noted that OMB announced in April 2026 that it would sunset the Dashboard in favor of a new streamlined system, without a release timeframe. GAO made 17 recommendations to nine agencies—including DHS, DOD, Treasury, and GSA—to correct understated ratings, update them on schedule, and align rating frequency with OMB guidance.
What it means for data and portfolio teams: a risk rating is a data element, and it needs the same governance as any other—an owner, a refresh standard, source evidence, and a quality check. Define the factors behind each rating (cost, schedule, performance, and risk-register status), tie each refresh to an evidence date, and flag any rating older than its required cycle as a data-quality exception rather than letting it default to its last value. If your agency is preparing for the Dashboard’s replacement, clean up rating lineage and timeliness now so the new system inherits trustworthy data instead of carrying stale “green” forward.
Source: U.S. Government Accountability Office, GAO-27-108416, “IT Dashboard: Selected Agencies’ Investment Ratings Fail to Fully Consider Risks,” October 7, 2026, gao.gov.
On October 7, 2026, the Government Accountability Office issued GAO-27-107676, Precision Navigation Systems: Challenges Remain with Fielding New Capabilities, a congressionally mandated review of the Department of Defense’s GPS modernization and complementary positioning, navigation, and timing (PNT) efforts. GAO reported that GPS modernization continues to face delays; in 2026, after years of delays, DOD canceled the Next Generation Operational Control System and began modernizing the existing GPS Operational Control Segment instead, which GAO says creates risks for launching, checking out, and operating new GPS satellites.
GAO found the Air Force is making progress on modernized military-code (M-code) receiver cards, but aviation receiver programs continue to encounter development and integration challenges, prompting the Navy to develop an interim solution for its aircraft. The Army and Navy are fielding M-code capable and multi-PNT receivers in ground vehicles, ships, and Army aircraft. The larger issue is portfolio fragmentation: a congressionally mandated PNT Oversight Council can recommend budget actions, but each service controls its own budget. GAO pointed to the Air Force’s M-code Aviation Receiver Joint Program Office—which combined aircraft PNT receiver and M-code receiver card efforts—as a model, and made three recommendations, with which DOD concurred, for the Army, Navy, and Air Force to assess where consolidation would improve strategic alignment and to develop consolidation plans.
What it means for program management teams: when several programs chase the same capability, an oversight council without budget authority cannot by itself synchronize schedules. Build a portfolio view that shows shared dependencies—such as common receivers, ground systems, and integration windows—alongside each program’s baseline, and make interface and integration milestones joint commitments rather than separate dates. Where consolidation is on the table, prepare the decision package early: overlapping requirements, funding lines, contract vehicles, and workforce impacts, so leaders can weigh a joint program office against coordinated but separate efforts.
Source: U.S. Government Accountability Office, GAO-27-107676, “Precision Navigation Systems: Challenges Remain with Fielding New Capabilities,” October 7, 2026, gao.gov.
On September 22, 2026, the General Services Administration published a proposed rule in the Federal Register (91 FR 60063; GSAR Case 2026-G501) to amend the General Services Administration Acquisition Regulation by moving Federal Supply Schedule (FSS) ordering procedures from FAR subpart 8.4 into a new GSAR subpart 538.71. The change aligns with the Revolutionary FAR Overhaul: FAR Case 2026-003 revises FAR part 8 and directs ordering activities to use FSS procedures established by GSA rather than keeping those procedures in the FAR.
GSA describes a single, dollar-threshold-based approach to order placement instead of today’s three-way split across FAR 8.405-1, 8.405-2, and 8.405-3. The proposal reorganizes blanket purchase agreement (BPA) content, relocates order-level materials (OLM) requirements from GSAR clause 552.238-115 into the ordering procedures subpart, and restates that FAR parts 5, 6, 14, 15, 16, and 19 generally do not apply unless otherwise prescribed. Comments are due October 22, 2026.
What it means for program and contracting teams: treat this as a desk-guide refresh, not a new Schedule program. Before the final rule lands, map your component’s FSS RFQ templates, BPA ordering procedures, sole-source justification packages, and OLM checklists to the proposed GSAR 538.71 structure. Confirm COR and ordering-officer training covers the clarified points that responsibility and fair-and-reasonable pricing are established at the FSS contract level, that FAR part 15 source-selection rituals are not required for Schedule orders, and that OLM use must remain secondary to the order’s primary purpose.
Source: General Services Administration, “General Services Administration Acquisition Regulation; GSAR Implementation of Executive Order 14275, Federal Supply Schedule Ordering Procedures,” proposed rule, Federal Register, September 22, 2026 (91 FR 60063; GSAR Case 2026-G501), federalregister.gov.
On September 24, 2026, the U.S. Postal Service Office of Inspector General issued audit report 25-139-R26, Postal Service Contract Practices and Oversight. Against more than $15 billion in FY 2025 managed spend, OIG found the Postal Service does not consistently collect and maintain required information to support informed contract decisions—raising exposure to improper payments and fraud. OIG identified $271,916,465 of monetary impact where required processes were not followed in FYs 2024–2025.
In a sample of 203 time-and-materials invoices, 151 (74 percent) lacked required descriptions or evidence of tasks performed in the contract system to justify payment; OIG projected at least $271.1 million in unsupported questioned costs for T&M invoices. Sixty percent of unauthorized contractual commitment (UCC) files lacked critical documents, and 18 percent of sampled noncompetitive purchases lacked evidence that required reviews and approvals were completed—even as the noncompetitive approval threshold had risen to $5 million. OIG also flagged decentralized oversight across portfolios and heavy reliance on manual workflows, with recommendations spanning invoice documentation standards, centralized UCC tracking, purchase-plan waiver policy, publicizing large noncompetitive awards, enterprise risk indicators, automation, and stronger excluded-supplier screening via UEI/TIN.
What it means for audit remediation and readiness teams: payment support is an audit control, not a COR convenience. Require T&M invoice packages to capture task descriptions tied to the order or PWS, sample COR invoice approvals against the clause checklist, and treat UCC and noncompetitive file completeness as continuous monitoring metrics—not once-a-year compliance sampling. When contracting authority is decentralized, stand up a short list of enterprise risk indicators (invoice support gaps, modification spikes, competitive-to-noncompetitive flips, excluded-supplier hits) that leadership can see across systems.
Source: U.S. Postal Service Office of Inspector General, Report Number 25-139-R26, “Postal Service Contract Practices and Oversight,” September 24, 2026, oversight.gov (PDF: 25-139-R26.pdf).
On September 21, 2026, the Department of Homeland Security Office of Inspector General issued OIG-26-30, CISA Enhanced Cloud Security for Federal Information but Lacks Authority to Require All Necessary Protective Actions. The audit examined how CISA’s Secure Cloud Business Applications (SCuBA) project helps Federal Civilian Executive Branch (FCEB) agencies secure cloud-stored information under Binding Operational Directive (BOD) 25-01, Implementing Secure Practices for Cloud Services.
OIG reported that CISA delivered tools, baselines, and extensive engagement—yet 88 of 102 FCEB agencies (86 percent) did not implement all mandatory SCuBA policies by the June 20, 2025 deadline, and 76 percent remained noncompliant as of February 12, 2026. Earlier milestones were also widely missed: 39 percent failed to inventory all cloud tenants by February 21, 2025, and 52 percent failed to deploy all assessment tools by April 25, 2025. OIG concluded CISA can develop and report on BOD compliance but lacks authority to compel full, timely implementation; the report contains no recommendations given that statutory limitation.
What it means for enterprise risk management teams: treat cloud-configuration baselines as residual risk you own, not as work that ends when a directive is issued. Map BOD 25-01 (and successor cloud mandates) into your A-123 / Green Book control inventory with a named accountable official, tenant inventory completeness metrics, and escalation when tool deployment or policy implementation slips. Where a central agency can only advise and report, component CISOs and program risk committees should close the gap with internal policy, continuous monitoring, and leadership dashboards that show noncompliant tenants before an OIG or FISMA cycle does.
Source: DHS Office of Inspector General, OIG-26-30, “CISA Enhanced Cloud Security for Federal Information but Lacks Authority to Require All Necessary Protective Actions,” September 21, 2026, oig.dhs.gov.
On September 4, 2026, the Department of War Office of Inspector General issued DOWIG-2026-120, a management advisory on the Defense Health Agency’s plan for a second sole-source bridge contract for Technology Lifecycle Support (TLS) services. OIG cautioned that successive bridges limit competition, constrain cost leverage and innovation, and deepen reliance on a single vendor while a follow-on acquisition is unfinished.
OIG found TLS tasks were not inherently governmental but included work closely associated with inherently governmental functions (for example, budget development and analysis informing policy), which requires heightened Government oversight and consideration of insourcing. Recommendations pressed DHA to evaluate insourcing TLS functions and pressed Acquisition & Sustainment leadership to confirm whether a second bridge is best value—or to direct an alternate strategy. Management responses described a time-limited second bridge plus a competitive follow-on path; OIG closed both recommendations based on those actions.
What it means for program and contracting teams: treat a second bridge as an exception that needs an explicit acquisition strategy, documented continuity risk, and a dated path to competition or insourcing—not a default calendar extension. Requirements packages for long-running IT services should separately identify closely associated functions, COR oversight capacity, and transition plans before option years or bridge awards.
Source: Department of War Office of Inspector General, DOWIG-2026-120, “Management Advisory: Concerns Regarding the Defense Health Agency’s Second Bridge Contract for Technology Lifecycle Support Services,” September 4, 2026, oversight.gov.
On September 2, 2026, DHS OIG issued OIG-26-25, FEMA Wasted Millions of Dollars in Public Assistance Small Project Grants. After Congress raised the Small Project threshold to $1 million, OIG reviewed a sample of 20 completed/closed projects (FYs 2023–2024) and found every sampled file missing documents or information needed to support approval and oversight. OIG questioned about $3.1 million in costs and identified about $7.9 million in over-obligated funds FEMA had not properly de-obligated (about $5.8 million already paid).
Root causes cited include weak design of simplified-procedure controls, acceptance of incomplete self-certifications and sparse damage evidence, and closeouts that did not recover identified over-obligations—including migration-related closeouts. FEMA concurred with recommendations on documentation/questioned-cost resolution and de-obligation recovery, and non-concurred with mandating photographic evidence for all damages/work; that recommendation remained open and unresolved at publication.
What it means for financial management and grants teams: simplified procedures are not “no documentation.” Programs that raise thresholds or streamline estimates still need enforceable minimum file contents in the system of record, controls that block closeout while over-obligations remain, and sampling of certifications against objective evidence. Treat de-obligation workflows as funds-control controls with owner, SLA, and exception reporting—especially after system migrations.
Source: DHS Office of Inspector General, OIG-26-25, “FEMA Wasted Millions of Dollars in Public Assistance Small Project Grants,” September 2, 2026, oig.dhs.gov.
On September 3, 2026, the Department of Commerce Office of Inspector General issued OIG-26-027-A on NTIA’s Public Wireless Supply Chain Innovation Fund award process for Notice of Funding Opportunity (NOFO) 1. OIG concluded NTIA had an adequate application review and award selection process on paper, but did not always follow it and could not appropriately support award decisions for sampled applications.
Recommendations focus on completing required documents before award decisions, ensuring decision memoranda are backed by program or grant files, analyzing eligibility with retained documentation, implementing quality-assurance for each review phase, and having the COR adhere to the Quality Assurance Surveillance Plan (QASP) when contractors perform initial/merit reviews. A related recommendation addresses NIST grants-officer oversight of specialist reviews under Commerce grants manuals.
What it means for program managers and CORs: a documented NOFO process only protects the agency if the file trail matches every decision. When contractors support merit review, COR surveillance under the QASP is a core control—not optional paperwork. Before selection boards finalize awards, require a completeness check that the decision memo, eligibility analysis, and reviewer workpapers are stored where auditors can retrieve them.
Source: Department of Commerce Office of Inspector General, OIG-26-027-A, “Audit of NTIA’s Public Wireless Supply Chain Innovation Fund Award Process for Notice of Funding Opportunity 1,” September 3, 2026, oversight.gov.
On September 1, 2026, the Office of Management and Budget’s Cost Accounting Standards Board published a final rule in the Federal Register (91 FR 56056; FR Doc. 2026-17901) raising Cost Accounting Standards (CAS) monetary thresholds and clarifying how CAS applies to indefinite delivery contracts. The rule is effective October 1, 2026.
Key changes for practitioners: the basic CAS applicability threshold for negotiated contracts moves to $35 million (implementing FY 2026 NDAA direction), the $7.5 million “trigger contract” concept is eliminated, full CAS coverage and Disclosure Statement thresholds rise from $50 million to $100 million, and agency-head waiver authority increases to $100 million. The rule also clarifies that CAS exemptions for multiple-award IDCs are assessed at the task/delivery order level, while single-award IDCs are assessed at award using the ceiling value.
What this means for program and acquisition teams: re-run CAS applicability for upcoming solicitations and awards dated on or after October 1; revisit Disclosure Statement and full-versus-modified coverage for mid-tier segments near the old $50 million line; and confirm IDC strategy language with counsel so order-level versus ceiling-level determinations are documented. Contractors currently under full coverage solely because of the prior $50 million threshold may transition to modified coverage at the next cost accounting period if they have no unresolved CAS noncompliances and no longer meet the $100 million test.
Sources: Cost Accounting Standards Board / OFPP, “Increase of Monetary Thresholds and Other Matters Related to Cost Accounting Standards Program Requirements,” final rule, Federal Register, September 1, 2026, federalregister.gov. Background on the Board’s mandate: Federal News Network, April 2026 coverage of the CAS Board comment process.
On September 4, 2026, the Department of Homeland Security Office of Inspector General issued OIG-26-28, CBP’s IT Access Control Deficiencies Introduced Critical Risk to IT Systems and Sensitive Information. The audit found that CBP did not consistently apply IT access controls: all tested network users incorrectly had access to a highly privileged service account; privileged functions were over-granted; not all applications were enrolled in periodic privileged-account review; and separated or transferred personnel often retained access beyond required timelines.
From an Enterprise Risk Management and internal-control perspective, the report maps directly to access-management control failures under DHS 4300A and NIST-aligned baselines: least privilege, timely deprovisioning, and continuous monitoring of privileged groups. CBP concurred with all 12 recommendations; several corrective actions target supervisor and COR notification discipline for employee and contractor separations.
What it means for program, acquisition, and COR teams: treat joiner–mover–leaver workflows as a control, not an HR handoff; verify that contractor offboarding in tracking systems triggers account disablement within policy windows; and ensure application owners can evidence periodic privileged-account reviews—especially for systems holding PII, law-enforcement, or biometric data. When OIG findings cite COR notification failures, acquisition leadership should reinforce COR desk guides and sampling of separation records.
Source: DHS Office of Inspector General, OIG-26-28, “CBP’s IT Access Control Deficiencies Introduced Critical Risk to IT Systems and Sensitive Information,” September 4, 2026, oig.dhs.gov.
In September 2026, the Social Security Administration Office of the Inspector General issued an Office of Audit report on Old-Age, Survivors, and Disability Insurance (OASDI) overpayment notices (report 152407, dated September 1, 2026). The objective was to determine whether SSA issued overpayment notices and processed explanation requests according to policy.
OIG found that a large share of sampled notices omitted policy-required information explaining how and when the overpayment occurred, and that explanation requests were not always handled as required. Incomplete notices impede individuals’ ability to seek reconsideration, waiver, or repayment options—and create rework when customers re-contact the agency without clear facts.
What it means for federal financial management teams more broadly: debt and overpayment communications are a funds-control and internal-control activity, not only a customer-service script. Programs that issue recovery notices should sample for required content (cause, calculation, rights, and repayment options), track explanation-request turnaround, and tie notice quality metrics to corrective action plans—especially where improper-payment risk is already elevated.
Source: SSA Office of the Inspector General, “Old-Age, Survivors, and Disability Insurance Overpayment Notices,” Office of Audit Report 152407, September 1, 2026, available via oversight.gov.
The November 2025 revision to DHS Directive 102-01 represents one of the most significant updates to the Department’s acquisition framework in years. With four new acquisition pathways, updated risk management requirements, and revised oversight gates, program managers and contracting officers across TSA and other components must adapt quickly.
Organizations that treat this as a compliance exercise will struggle. Those that use it as an opportunity to streamline their internal processes and upskill their workforce will gain a competitive advantage in speed and mission outcomes.
M2 Torres Recommendation:
Schedule a tailored workshop on the new Directive 102-01 pathways and risk framework. We’ve already delivered this content to multiple TSA audiences with excellent feedback.
In the current fiscal environment, every program dollar is under the microscope. Congressional staff, OMB examiners, and component leadership are demanding clearer linkages between mission requirements, performance outcomes, and requested resources.
Programs that master this traceability are seeing faster approvals and fewer marks. Those that don’t are experiencing delays and reduced funding.
M2 Torres Recommendation:
We help teams build stronger PPBE artifacts and train analysts on justification techniques that resonate with reviewers. Many of our clients have used our frameworks to successfully defend resources in tight cycles.
Closing audit findings quickly is necessary but not sufficient. The agencies seeing the biggest reduction in repeat findings are those treating remediation as a strategic capability, not a compliance fire drill.
Sustainable remediation protects mission resources and builds long-term organizational resilience.
M2 Torres Recommendation:
Our audit remediation support combines hands-on corrective action planning with training that builds internal capability. Clients typically see measurable improvement in repeat finding rates within one to two cycles.
Practical frameworks and checklists you can put to work immediately. Full branded PDFs of the above articles available upon request.
Key checkpoints for new programs, PPBE alignment, and audit readiness.
Practical templates and steps for identifying gaps and preparing for successful audits.
Branded PDFs of featured articles available upon request.
Request via Contact Form →